Progress is officially underway at United Commerce Center in West Bridgewater, MA.
January 7th, 2026
Progress is officially underway at United Commerce Center in West Bridgewater, MA.
The site is cleared and prepped, and we are getting ready for pre-load ground improvements before starting foundations on two new buildings totaling 310,000 SF.
Next up: Cut-to-fill on the North building & import of 100K tons of structural fill for the South Building.
Stay tuned for milestone updates as this one comes out of the ground.