Integrated Builders completed, in less than 6 months, a 50,000 s.f. data center for Network Plus in Braintree, MA. The process encompassed the completed renovation and upgrade of the company’s existing “Butler” building. The exterior components of the renovation included new roofing, side panels a parking lot, drainage system, and extensive landscaping. The mechanical system upgrades included a three, 400 ton air cooled chillers, and 34 interior zones of cooling. The property’s electrical service required the installation of two 2,000 KVA transformers, and two 400 amp busways together totaling 8,000 amps of new power. Two 2,000 KVA/2,500 KVA diesel generators with two, 5,000 gallon tanks were also installed as well as four, DC power plants and a fire alarm system.