« Back
Progress Update - South Shore YMCA Addition
December 8th, 2025
Progress Update - South Shore YMCA Addition
Exterior finishes are wrapping up, and paving prep is underway. Inside, spaces are taking shape with paint on the walls, carpet going down, tile set, and casework installed. We’re also tying the addition into the existing building, bringing this project close to the finish line.
Posted in the category Project Updates.