Integrated Builders is making great progress in Westminster as the interior piers, grade beams, and foundation walls are the major push for the next 30 days. Significant sitework is also advancing both inside and outside the building footprint. Precast wall panels are set to arrive in the first week of February. Superintendents Herb Volpe and Josh Donohoe are doing an excellent job overseeing underground plumbing, foundation work, waterproofing, and sitework coordination!